Slab pre-pour inspection in Oran Park

Collars, steel and formwork, in the hours before any of it becomes concrete.

  • The day before the pour, steel and formwork complete
  • About 1 hour on site
  • Report within 24 hours
Price your Oran Park inspectionSend the address and the stage due.

Fully licensed & accredited

Stage2 of 7
When to bookThe day before the pour, steel and formwork complete
Time on siteAbout 1 hour on site
Inspected againstAS 2870, AS 3600, NCC Part 3.2, the engineer's slab design and the soil report

What is included in a Oran Park slab pre-pour inspection

  • Slab class and layout checked against the engineer's design and the soil report
  • Edge beam and internal beam depths and widths
  • Reinforcement size, spacing, laps and trench mesh
  • Bar chairs, cover and support so steel does not sit on the ground
  • Waffle pods, void formers and pod spacing
  • Vapour barrier coverage, laps and tape at penetrations
  • Plumbing and electrical penetrations and sleeves
  • Set-downs for wet areas, garage, porch and alfresco
  • Termite management components installed before the pour
  • Formwork alignment, level and set-out against the plans
  • Stormwater pipe cover and pit positions where visible
  • Site cut, fill and pier holes where visible
  • Hot water service and meter box slab extensions formed
  • Trench cleanliness and debris before the pour
Why it matters here

Slab pre-pour inspections on Oran Park builds

This is the best documented stage we have in Oran Park and the one that produces the findings people remember. Termite collars not fitted at slab penetrations, which leaves a concealed route from soil to structure sealed permanently in place. Re-entrant corner reinforcement not installed, which is the steel that controls shrinkage cracking at internal corners. Cover short of the minimum. Beam widths inconsistent. Vapour barrier joints unsealed. None of it is visible an hour after the truck leaves.

What we find at this stage in Oran Park

  • Termite collars not installed at penetrations
  • Re-entrant corner reinforcement not installed
  • Concrete cover below the minimum
  • Beam widths inconsistent through the raft
  • Vapour barrier joints unsealed or needing adjustment
Beam width varying through the raft, Oran Park
Beam width varying through the raft
Sample findings

Sample defects found during our slab pre-pour inspections in Oran Park

Annotated findings from Slab pre-pour inspections on Oran Park builds. Client addresses withheld.

Termite collar not installed, recorded during a slab pre-pour inspection in Oran Park
Termite collar not fitted
Re-entrant reinforcement not installed, recorded during a slab pre-pour inspection in Oran Park
Re-entrant corner steel absent
Insufficient concrete cover, recorded during a slab pre-pour inspection in Oran Park
Cover below the minimum
Vapour barrier joints not sealed, recorded during a slab pre-pour inspection in Oran Park
Vapour barrier joints unsealed

The other stages of a Oran Park build

  1. Bored piers inspection in Oran Park1Bored piersAfter boring and cage placement, before concrete
  2. Frame inspection in Oran Park3FrameOnce frame and trusses are up and the roof is on, before lining
  3. Lock-up (pre-plaster) inspection in Oran Park4Lock-up (pre-plaster)After roof, cladding and external doors, before plaster
  4. Fixing inspection in Oran Park5FixingAfter mouldings, doors and joinery, before the painter
  5. Waterproofing inspection in Oran Park6WaterproofingAfter the membrane is applied and before any tile is laid
  6. Pre-handover (PCI) inspection in Oran Park7Pre-handover (PCI)Two to three weeks before your handover date

All construction stage inspections in Oran Park →

Guides

Construction stage guides for Oran Park

All guides →

Book a slab pre-pour inspection in Oran Park

Instant online pricing, or talk to the booking team on 1300 471 805.

FAQ

Slab pre-pour inspections in Oran Park: common questions

What is re-entrant reinforcement?

Extra steel placed diagonally at internal corners of the slab, where the geometry concentrates shrinkage stress. Without it, that corner is the place a crack starts, and it is a controlled crack rather than a structural failure but it is avoidable.

Why do collars matter so much at this stage?

Because after the pour the penetration is sealed around whatever is or is not there. A collar fitted afterwards is not the same thing, and retrofitting is a far more involved job.

Does looking at a finished slab achieve anything?

You can look at the surface. You cannot look at cover, at collars or at the steel inside it. Which is exactly why this stage exists.

And if the pour is delayed?

We reschedule to match, without a fee. Dates shift constantly and it is never a reason to skip the stage.

What is the duration on site?

An hour to ninety minutes on a standard lot, with the report generally out the same evening so the builder can act.

Do you check the meter box set out?

We record it where visible. We have found the box and conduit not installed at pre-pour stage here, which is far easier to correct before the slab than after.